Result Analysis - Planned Data without Secondary Cost

$
0
0

Hi All,


I'm using result analysis method 01 and when I'm running KKA2, I found that the secondary costs are excluded from planned data as shown in the screenshot below.

RA.png


May I know what is the reason? I'm running EHP7.


This is the planned data from standard report S_ALR_87013531 - Costs/Revenues/Expenditures/Receipts

Report.png

Note: The planning are done using WBS-Network and Activities attached to it. Activity (cost) with primary cost element are showing in the RA but not the activity using work center/activity type (secondary cost element).


Any idea what's the reason?


Thanks,


John