RPSCO table doesn't update!

$
0
0

We find  the RPSCO table for our project isn't updated after running CJEN.For one WBS of our project,we find the value for the wbs in RPSCO is wrong.and it is not consistent with the vale in table COEP and COSS\COSP.We use the cjvc to  check the value category ,the light is green.it seems no problem.and we use  cjen and cjbv  to regenerate the RPSCO table and re-active the buget availibility control.After we did it,the value for the WBS has no change.

For this reason ,it result in the project cost value  from cji3 is not equal to the value from S_ALR_87013557.We try many ways ,but it is no effect so far.

How to solve the problem?Thanks a lot.