Quantcast
Channel: SCN : Unanswered Discussions - SAP Project Systems (SAP PS)
Viewing all articles
Browse latest Browse all 772

Plan value coming as assigned Value

$
0
0

Hi Experts,

 

I am doing network costing, and rolling up to WBS through Project simulation, and finally converting it into Operative project.

 

Now the issue is that suppose

 

     wbs1  - cost plan value = 500,

 

when i am trying to allocate budget , in cj30, this value is automatically copying into Assigned value.

 

I have activated the Budget AVAC, with thresholds at 90 percent. Now if i am totaling up planned value and assigning the same to Budget, it is giving Busget exhaust error.

 

Effectivey, to give a Budget of 500, I have to allocate duble the Budget i.e. 1000 ( to counter the assigned values coming by Planned values (from networks cost).

 

If the system is behaving normally, then how should I be able to arrive at cost planning and give budget accordingly with AVAC.

 

 

PLease reply with your inputs.

 

Regards

Rohit


Viewing all articles
Browse latest Browse all 772

Trending Articles