hello
I have such scenario.
I know that I will have new project in this year, eg building apartments. This will be short half year project. But I don't know the phases of this project I don't know anything about this project, budget etc. So I can create a project definition and I would like to reserve some specialists of my company workforce. I suppose that this contract will start in Q2 in this year, so I would like to do reservation of workforces in order to other project in my company won't utilize this workforce during Q2 i Q3. Is there any option how to do such reservation of workforce?
Regards
Adam