Hi All,
In one of our projects in CJ20N, the user has done multiple iterations of TECO (Set and Undo) and CLSD (set and undo). After these multiple iterations, when the projects was finally closed by the user, the project shows active status as REL as well as CLSD. How is this possible ? Shouldn't the REL status become inactive when the project is CLSD ? How can the project have these two active status at the same time?
Has anyone come across such scenario ? Any suggestions ?
Screen shot attached below