Budget available in WBS but popping budget exceeded error

$
0
0

In a WBS, CNS41 displays budget available but when a service indent is being created it is throwing a budget exceeded error. I have checked in OPS9 the budget control is already active. I have executed CJEN and CJBN. Yet the same error persists. I have checked t-codes CJI3, CJ76, S_ALR_87013557, S_ALR_87013543 etc.

Please help.

 

Regards,

Esha