Hi,
I have a request whereby user have asked to remove budget checking via project and request for it to be done at IM position level @ to move AVAC from project to IM position.
Let say the IM structure is like this:
L1 Company A
L2 Division A
L3 Business Area A
L3 Business Area B
L3 Business Area C
L4 Project Type A
L4 Project Type B ($1Million)
L5 Project Definition TA ($1Million)
L5 Project Definition TB ($1Million)
Budget from IM Project Type B has been distributed $1 million both for TA and TB and current available budget for IM Project Type B is $1 million.
Current setup is to have AVAC on project level whereby utilization of more than $1 miliion will not be authorized.
User have requested to remove AVAC checking on projects to allow utilization of additional $1 million which is currently available at IM Project Type B.
Once the money at IM Project Type B is depleted, then only TA or TB will encounter error insufficient budgetting.
Basically budget checking @ AVAC is to be done at L3 instead of L5.
Can this be done?
Your feedback is much appreciated.
Fadhil