Unable to do final settlement WIP - results analysis - in a project

Hello All, We have set RA for projects. This is MTO scenario. All actual costs of project in Release status are calculated as WIP in top WBS.For periodic settlement, this is getting settled to B/S and...

View Article


Userfield tab at WBS element level

Hi Experts, I am able to see User-field tab at Network Acivity level but NOT at WBS element level.I don't see Userfield tab at WBS element level. We don't maintain Field Key in Project profile.We will...

View Article


PR or PO not triggering activation control as per the set tolerance limit

Hi, I created as belowProject - 100008 (without investment program ID) - StandardWBS (level-1) - 1000081WBS (level-2) - 1000082WBS (level-3) - 1000083 CJ30 - created overall budget - $1000. Created PO...

View Article

block actual or commitment cause by foreign exchange difference

Dear PS Expert, i have a foreign exchange case, let's say that i have US$ 10.000, then i open PO for 1 qty with net price IDR 1.400.000 with rate 1 US$ = IDR 140. then post goods receipt the next day...

View Article

Modules Linked to Project System

Hello Team, I am currently working in Project system , could you please suggest for some other modules which can be learned asI see very less projects and oppurnities  in industry when PS module is...

View Article


Capitalized Interest - Variable rate interest business case

December 22, 2015What has been your experience in configuring a capitalized interest business case with a variable interest rate. This is the business case which the interest rate will change from one...

View Article

Userfield Character Lenght

Hi, We are trying to increase the character length of User field from 20 characters to 24 characters? Are there any User-exit to do so?

View Article

Activity release date

Team, Have got a doubt. I want to know  the  release date of an Activity/ Activities in a network of Project ..Which field in table /database holds this information.Also is there any way to get that...

View Article


Image may be NSFW.
Clik here to view.

problem in translation

HiI need to change the word "Internal Processing" when creating new activity in a project. I did anything that I knew but it didn't affect.  Can anyone help me? Regards

View Article


Restrict user for changing and release budget for level 1 WBS

HI Experts, Can anyone help me through this - I want to restrict some user to change in level 1 wbs budget either original or release.For e.g. below is the WBS structure of my projectC-15TST01...

View Article

SAP PS S_ALR_87013611 report

Hi,We want to see WBS element in this report.When I click on the 'Actual Line Item' ,I see costs at Network Activities level since we use NWA to capture costs.Can we add corresponsidng WBS element...

View Article

system behavior while choosing pr for network in cj20n

Dear PS experts,      when assigning a material component to an activity in CJ20N and choosing item category N then choosing Pr for network. the system asks me about the delivery address for this item....

View Article

PS BBP required

Hi  Please can you send me the PS BBP to my email id debtosh@gmail.com? Thanks in advanceDeb

View Article


Image may be NSFW.
Clik here to view.

Error G/L Account doesn't exist in CJ20N

Dear Gurus,I have a service number for Building Rent which assigned to Balance Sheet Account (Rent Account). When it was used in PR (account assignment "K" Cost Center) the result was OK, then we used...

View Article

WBS element in location tab and additional tab of PM order.

Hello SAP Folks, Can anyone suggest any BAPI, for updating PM orders with WBS elements in additional tab and location tab. Thanks and regards,Neha

View Article


Settlement Rules

Hi All, I am new to PS. Does anyone know any bapi/fm for Settlement rules, for getting details and upload  Regards

View Article

Copy Project with User Status

Dears, Kindly I need to  know if their is any option to copy a WBS with activities from a project to a new project with their user status  Regards,Allaa Waked

View Article


Number of Activities

Hi experts How many activities can be created in a network?

View Article

No costs, revenues or finances are selected Message no OK602

Hi, In report S_ALR_87013558 for one the user, system gives error message for one network as No costs, revenues or finances are selected Message no OK602 but for other users there is no error message...

View Article

RG1 update by using invoice based billing

Dear Experts: we have the same issue. Now we made testing with order based billing. the only missing link is the update of the quantity in the RG1 register. See enclosed documents - one is the way how...