FM KBPP_EXTERN_UPDATE_CO - Fiscal year is not in the time frame > Check profile
Hi Gurus, executing the FM KBPP_EXTERN_UPDATE_CO I'm facing the error (message BP 088) Fiscal year is not in the time frame > Check profile &. Before the creation of a new budget profile and a...
View ArticleSettlement rule error
Hi Experts, I have created WBS released and system status set as AUC, but now I am defining settlement rule and system throws me error, please suggest where I am lacking. RegardsAbhishek Singh
View ArticleHow do you display all WBS Codes ever created in one list?
Hi, I am looking for a way to display all WBS Codes ever created on SAP in one list. Could you provide me with a transaction and a method for doing this please? I have used CJ20N to set up the WBS...
View ArticlePOC is not aggregated from Activities to WBS
Hi All, I am doing progress analysis based on quantity proportional method. If i plan and post SKF on WBS , and run CNE1 , i can see the POC aggregated to higher level WBS. But i am not able to do the...
View ArticlePlan values vs actual values
Hi all, In an activity , I am giving the work : 100 m3Plan values : Activity price planning (KP26) i am maintaining as Rs 300. When i confirm the activity my plan values only becoming my actual...
View Articleproblem with result analysis poc method 07
Dear SAP experts, We are using result analysis with POC method 07 where we enter an estimate % on the WBS by month and we calculate the results based on planned costs & revenues. We are getting the...
View ArticleReport assignment for IM report painter
Hi All In one of my IM report painter reports that I am working I need to go to line item report after the output:1. Internal Orders/WBS commitment line items2. Internal Orders/WBS plan line items3....
View ArticleProfit center valuation is not active
Hi Experts, Transaction Code : CJF1,CJF2, CJF3 I am getting Error in initial screen when define Set Controlling Area, It shows error “Profit Center valuation is not active” I tried OKKP and select the...
View ArticleCJBN for budget availability activation
Hi All, Can anyone tell me if I have created project so when ever I create project and before assigning budget on multiple project I have to run 'CJBN'? is there any other way that it will run...
View ArticleList of notification for WBS
HI All, We are creating notification to capture certain event like inspection to capture snags and related data and assigning it to WBS (Location Data: Account assignment). Issue is we are not able to...
View ArticleHow to carry out Project scheduling after adding network activity with BAPI?
Hello,We have developed a SAP UI5 application for Project Systems. We have a feature of adding network activity to a SAP PS project. The BAPI used to do the same is ' BAPI_BUS2002_ACT_CREATE_MULTI '....
View ArticleProject Number Validation
Dear All, Need your advise how to do a validation for the below scenario. Project Number Suppose to be Z-00001, where as system allowing to maintain Z-00001-1 and Z-00001-1-01 as well, which I need to...
View ArticleHow to delete all the wbs's settlement rule
Dear SAP Guru's,I want to delete the settlement rule from all the WBS element in a project without any z development.Can you please suggest any way.RegardsSK
View ArticleExchange Rate - PS/FI
Hi Experts, For imported material & services, PR and PO are issued in foreign currency. Budget validation in PS now is taking the exchange rate as of the date of creation of documents. Later when...
View ArticleProgress analysis with budget as EV basis
Dear PS Experts, I am debugging a progress analysis with budget as EV Basis. Budget is connected to Investment measure. Budget is maintained in WBS elements. Progress version has Earned Value Basis:...
View ArticleNetwork Activity Budget Exceeded Message no BP601
Dear All, When the user tries to create the PR on the activity 1280 , Budget Exceeded Error is displayed but we have enough Budget The detailed error Message is Payment Budget for WBS Element X123.03...
View ArticleItem Text filed In Cj20N screen
Mates, What is the Item text field in a Cj20N screen. Can user type in some custom text over there. RegardsMandan
View Articleby pass authorization check for BAPI_BUS2054_SET_STATUS (to remove user status)
hello all, we have developed a Z-Program to remove ACF(user) status for a given WBS, for this we have used BAPI = BAPI_BUS2054_SET_STATUS however this BAPI is checking for authorization (throwing...
View Articlederive structure execute
Hi The project structure (wbs elements) i have maintained is like this - P.01 P.01.SD P.01.MM P.01.PP It's ok if I dont use Derive Structure function. At clicking on Execute from the...
View ArticleAssign and Reserve Resources
Hi, We are implementing SAP PS module and will need to do soft booking (reserve) of some resources for a project.It is possible to do this and how it can be done, at a project level. The "split...
View Article