Project Scheduling on Actual dates of Activity

$
0
0

Dear All,

 

Can we schedule a Project after actual Confirmation of Internal Activity.

 

Scenario: I have a project with start date 01.01.2014 and end date 31.12.2016. with some Activities with Relationship and Scheduled.

 

 

                      Basic Start Date        Basic Finish date      Actual Start Date           Actual Finish Date

Activity 1          01.01.2014               15.01.2014               01.01.2014                    15.01.2014

Activity 2          10.01.2014               20.01.2014               10.01.2015                    20.01.2015

 

due to some reason there are a Delay of 1 year in the Schedule. Now  i want that further Activities be scheduled According to the Actual Start Date of Second Activity. is is possible in Standard system. or what is the Procedure to adopt this.

 

Thanks

Govind