Dear All,
Can we schedule a Project after actual Confirmation of Internal Activity.
Scenario: I have a project with start date 01.01.2014 and end date 31.12.2016. with some Activities with Relationship and Scheduled.
Basic Start Date Basic Finish date Actual Start Date Actual Finish Date
Activity 1 01.01.2014 15.01.2014 01.01.2014 15.01.2014
Activity 2 10.01.2014 20.01.2014 10.01.2015 20.01.2015
due to some reason there are a Delay of 1 year in the Schedule. Now i want that further Activities be scheduled According to the Actual Start Date of Second Activity. is is possible in Standard system. or what is the Procedure to adopt this.
Thanks
Govind