Dividing one project to many projects
Dear PS experts, We are implementing a construction project and I am confusing a bout handling a project with the case of the customer.the customer has a department of electricity work and he...
View ArticleRuntime error in constraint restriction: #2 BOM_GROUND_CONTROL
Hi Expert , Getting below mention error while using Configure Material in CJ20N. ***********Runtime error in constraint restriction: #2 BOM_GROUND_CONTROL Message no. 28472 Diagnosis A runtime error...
View ArticleOptimize Selection Variant for Progress Analysis
Hi Experts, We have a certain selection variant for progress analysis being used in background job which is taking lot of time. Sometimes causing the job to fail.I was taking an initial look at the...
View ArticleCost Recognition based on Percentage of Completion
Dear Expert, Nowadays, we are implementing SAP PS to handle Plantation and Farming Business Operation.One Block of Plantation area is defined as 1 WBS. All of operational Cost in this Block will be...
View ArticleMass settlement rule upload for updating Multiple WBS
Hi Experts,I have AUC creation setup for CAPEX projects where AuC is auto created upon WBS release. After posting all the cost to be capitalized,AuC settlement run is executed month end using line item...
View ArticleProject Scheduling on Actual dates of Activity
Dear All, Can we schedule a Project after actual Confirmation of Internal Activity. Scenario: I have a project with start date 01.01.2014 and end date 31.12.2016. with some Activities with Relationship...
View ArticleTECO NOT POSSIBLE DUE TO STOCK (AT PROJECT DEFINITION LEVEL)
Dear All, We are facing problem while trying to set system status TECO at project definition level. (Customer Projects) "TECO NOT POSSIBLE DUE TO STOCK" message appearing while trying to save. There...
View ArticlePlan cost inconsistency
Hello colleagues, I need some help from you. When we plan costs in a network activity, the parent WBS element will also show those costs in a report(cost element, for example). My problem is that when...
View ArticleBAPI to update CJR2 Revenue Plan
Hi Experts, We are planning to create a program to update revenue plan in CJR2.What should be the best way to do it? Basically the custom program does some calculations and then updates the revenue...
View ArticleTable for confirmed hours after posting to CO
Hi Experts, I am looking for a table which gives me number of hours booked on a WBS/network activity. Booked either via CATS timesheet or direct confirmation of activity. We are planning to use this...
View ArticleBudget check @ GI scenario
Dear Experts, I have a scenario as below:I want to exclude the project PO from budget check, but want to have the budget check @ GI. I have tried this in my system but could not succeed. In config I...
View ArticleProject Progress by WBS & Activities Weightage
Dear All, How to measure Project Progress from weightage of both WBS and Activities.Pl refer the below table. like I have Two WBS and the weightage of WBS is 40% and 60%.and in each WBS there are 3-3...
View ArticleSAP PS budget against PO commitment
Hi,We have created PO with 2000$ against the WBS element but GR is done for 1000$ which is an Actual cost against that particular WBS element. As per Standard SAP, the remaining committed value (1000$)...
View ArticleKeep advanced procured material in project stock
We have a material with procurement key "F" and individual/collective (mrp4) setting "individual". We are use the project builder with a component created for purchasing the material in advance. In the...
View ArticleProject Changes
Hi experts, My question is; what are the steps to perform if the project business area, plant and profit center is changed? The project is released and there are financial activities on project. Thanks...
View ArticleIdocs not generated on Status change of Network
Hi SAP Experts , We are trying to trigger IDOCS for any status change of networks .IDOCS are getting triggerred for any cosmetic changes , but whenever we are trying to change the status of Networks...
View ArticleCJV4 error Version to Operative - A planned order still exists
Dear X'perts, Please help me out as I am facing an issue while transferring version to operative where I get the error " A planned order still exists". Does the fact that there Deletion flag set on a...
View ArticleHow to find who applied filter in S_ALR_87013542.
Dear Experts, Is there a way to find who applied filter in report S_ALR_87013542 for a particular column?As shown here: Kindly suggest your ideas on it.Thanks
View ArticleRA Key with No result analysis
Hi Experts Probably a very basic question.If I have a customer T&M Project where I want to recognize revenue as its incurred and recognize cost as its incurred, Do I really need a result analysis...
View ArticleStandard SAP report on WBS element status change
Hello people. Today I read some discussions about the subject of my question. But I didn’t find the answer I'm looking for: is there some standard report where I can see the changes of a WBS element?...
View Article