Hello colleagues, I need some help from you.
When we plan costs in a network activity, the parent WBS element will also show those costs in a report(cost element, for example). My problem is that when I physically delete the network activity without first removing the planned costs, the costs will keep showing in the report for the WBS element. That is a big inconsistency, in my opinion, but SAP says that this is normal behavior.
Anyone knows how I can avoid this? My users want me to do write ABAP code to delete those planned costs from the WBS, but I do not want to go so far and would prefer an easier solution.
Thanks in advance.