Dear PS experts,
I have an issue while making project scheduling i have a project as below:
WBS 1 ---------------
Act 1 -------
ACT 2--------
WBS2-----------------
ACT 3--------
ACT4 --------
all the activities is FS relationship
when i trying to change the relationship between act 2 and act 3 to be SS
scheduling conflict happened as the dates of ACt 3 , 4 and WBS 2 doesn't changed .
my scheduling method : WBS determine dates so the dates of the WBS should be cleared manually and after that making scheduling
I have attach a file of my scheduling configuration.
and i am asking if anyone have automatic solution for this issue ???