Aggregated Planned POC and BCWS

$
0
0

Dear PS Gurus,

 

The question is regarding the relation of Aggregated Planned POC, Planned Cost with BCWS.

 

WBSPOC WtAggregated POCNon Aggregated POCPlanned CostBCWSExpected Results of BCWS
BBCDEFG=E*(C/100)
WBS Element 1                  572,500                     10.823 0    216,128,460.02       26,412,097.61       23,392,366.58
WBS Element 1.1                    65,000                       9.615                       9.615       23,145,871.39         2,225,475.53         2,225,475.53
WBS Element 1.2                  200,000                     12.857                     12.857     178,976,661.34       23,011,029.35       23,011,029.35
WBS Element 1.3                  300,000                     10.000                     10.000       11,755,927.29         1,175,592.73         1,175,592.73
WBS Element 1.4                      7,500                               -                                -          2,250,000.00                               -                                - 

,.

In Expected Result column of above table, the value of WBS Element 1 is calculated based on the Planned Cost 216,128,460.02 and Aggregated POC 10.823 where as BCWS of WBS Element 1 is 26,412,097.61 which is simple total of lower level of WBS Elements (1.1, 1.2, 1.3 and !.4).


Please guide / help how SAP is relating these three values and aggregation of BCWS.

 